Hi all,
Wondering if anyone cares to share their insight, tips, and past experience on this.
As some previous posts state, I am looking into extracting data from an AIX system, using TSM/Centera, into a new system using Linux/ICOS. I am trying to put an actual timeframe on how long it is going to take to extract from AIX, and reload into Linux. I have the extract/reload process down mostly, but I am not sure where to start as far as coming up with solid dates.
There is a total of around 7TB of data to extract, totaling 200 Million Documents across 32 application groups. The totals of data in our app groups range from a few hundred MB, to 4.5 TB.
I understand there are SEVERAL variables to consider as far as this entire process goes, but does anyone have any suggestion as to how I can use our logs to actually put some realistic numbers to this.
Thanks in advance.